Soil removal nearly complete for building subgrade.Site set to subgrade. Once dried-out, soil will be compacted and covered with stone for new warehouse slab.Concrete reinforcing wall form work underway.Concrete retaining wall form work and temporary catwalk underway.Tank form pad reinforcing steel. When complete, three layers of #8 reinforcing steel on 8″ centers in a 30″ thick concrete slab supporting fourteen tanks.Concrete retaining wall, form work recently removed. Awaiting seven day cure period and waterproofing before backfill.